Task 2 Manage project quality | My Assignment Tutor

Assessment Task 2 Manage project quality BSBPMG532 Student Declaration To be filled out and submitted with assessment responses ◻ I declare that this task and any attached document related to the task is all my own work and I have not cheated or plagiarised the work or colluded with any other student(s) ◻ I understand that if I am found to have plagiarised, cheated or colluded, action will be taken against me according to the process explained to me ◻ I have correctly referenced all resources and reference texts throughout these assessment tasks. ◻ I have read and understood the assessment requirements for this unit ◻ I understand the rights to re-assessment ◻ I understand the right to appeal the decisions made in the assessment Unit Title Unit CodeStudent nameStudent ID numberStudent signatureDateTask Number ——OFFICE USE ONLY—– For Trainer and Assessor to complete:◻ Student requested reasonable adjustment for the assessment MarkingCompleted successfullyDid the student satisfactorily:CommentsYNDNSThe student has satisfactorily completed and submitted the following:Notes from the briefing session in week 1 in Task 2.1A Project quality management plan in Task 2.1B Summary of agreed on changes to the quality management plan in Task 2.1C Summary of feedback and inputs into the project quality plan in Task 2.2 Project quality management plan in Task 2.2☐☐☐The student actively participated in the briefing session with the project sponsor in week 1 of class (Role-Play in simulated work conditions): Asked questions relevant to project quality planning Listened actively Took notes☐☐☐The student presented the project quality plan to relevant stakeholders in week 3 of class (Role-Play in simulated work conditions): Confirmed quality objectives and standards Discussed and confirm quality metrics and requirements for each project deliverable Negotiated proposed roles and responsibilities for project quality management Confirmed quality assurance and control processes and practices Demonstrated support for the quality management plan Used active listening and questioning to elicit views and opinion of others Documented feedback and inputs from the group of stakeholders Adopted a collaborative approach☐☐☐Agreed on changes to the project quality plan were applied.☐☐☐The student attended the meeting with the marketing team and the project sponsor in week 3: Identify the quality objectives and standards in consultation with the marketing team Consult with the marketing team on quality requirements Consider inputs from the project sponsor, played by the trainer and assessor in simulated work conditions Listened actively☐☐☐Demonstrated ability to: Identify quality objectives and standards with input from relevant stakeholders Develop quality metrics for the project and any product output in a quality management plan Select quality management methods and tools for resolving quality issuesThis is evidenced by: Notes from the briefing session in week 1 in Task 2.1A Project quality management plan in Task 2.1B Summary of agreed on changes to the quality management plan in Task 2.1C Summary of feedback and inputs into the project quality plan in Task 2.2 Project quality management plan in Task 2.2 Active participation in the briefing session with the project sponsor (Refer to marking sheet) Active participation in the meeting with relevant stakeholders in Task 2.1C and Task 2.2.1 (refer to marking sheet)☐☐☐Demonstrated ability to: Consult with project team and stakeholders on quality requirementsThis is evidenced by: Notes from the briefing session in week 1 in Task 2.1A Summary of feedback and inputs into the project quality plan in Task 2.2 Active participation in the briefing session with the project sponsor (Refer to marking sheet) Active participation in the meeting with relevant stakeholders in Task 2.1C and Task 2.2.1 (refer to marking sheet)☐☐☐When collaborating with the group, the student has actively participated in group work with a substantial contribution that can be assessed individually for all the requirements of this task.☐☐☐Task Outcome: Satisfactory ☐Not Yet Satisfactory ☐Student Name:Assessor Name:Assessor Signature:Date: Table of Content Student Declaration 2 Task 2 – Determine quality requirements 6 Task 2.1 Determine quality requirements 10 Task 2.2 Case Study 15 Task 2 – Determine quality requirements Task summary and instructionsWhat is this assessment task about?Refer to and read the documents saved in a separate folder:MMI company profile and project task Policies and ProceduresYou have been recently engaged by XYZ Pty Ltd trading as MMI as a Project Manager (PM) to develop and implement a project to open a new campus in Sydney (refer to MMI strategic objectives).The Board of Directors (BoD) has allocated 3 million dollars to the project. Project duration: 1 year. You can employe four new staff members to be part of the project team for its duration. Source the rest of the project team from existing MMI personnel (flexible work arrangements will be needed)The project includes:Finding premises in Sydney CBD ( 800-1000 square metres, onsite parking for staff, natural light) Ideally, there will be enough room for 5-7 classes, one meeting room, one computer lab, 1 x student kitchen, student lounge, 1 x staff kitchen, three offices for staff, toilet facilities Rent the premise Obtain necessary permits Source architect and building company Source and buy furniture and equipment Liaise with the architect and building companyThe project steering committee is composed of:Mr Eli Brown – Non-executive DirectorMr Leonard Black – CFO Academic Manager (Jacob Graham)The project sponsor is Taylor Varin (Client Service Manager), played by the trainer and assessor.You will have to:Determine the project requirements Work in collaboration with pertinent stakeholders Scope the project Cost and resource the project Develop the project plan Execute the project Finalise the projectEach unit covered in your Diploma of Project Management will address a part of the project:Scope Time Quality Cost Human Resources Information system and communication Risk Project Integration Communicate with influence Facilitate continuous improvement in project work Develop project workplace policy and procedures for sustainability Lead and manage project team effectivenessBSBPMG532 addresses project quality.Having a clear vision of the project and its structure will help you plan and implement it in simulated work conditions.Your trainer and assessor will provide support and mentorship in the role of Project Sponsor (PS).You will work in a project team of max four students. You will both lead the team and be a part of it to experience different project roles in the simulated work environment, project manager being the main one. Take turns playing the role of PM when the task requires project team collaboration. The trainer and assessor will observe project work and provide feedback on the Marking Sheet.Form or join a project team (3-4 students in the team). Document the name of the students in the table below:Student NameStudent NameStudent NameStudent NameYou will collaborate with the project team in a simulated work environment to carry out the responsibility of your role as a PM relevant to quality management.Although you will lead and collaborate with the project team, your assessment’s work must be individual, and it will be marked as such.Please note that the performance evidence for this unit of competency requires you to demonstrate the ability to manage project quality on at least two occasions. This assessment has been designed to meet that requirement.This task comprises of the following assessment methods: Product-based ☒ Direct observation of Role-Play ☒ Case Study ☒ Other (specify) ☐It has been designed to evaluate your ability to/competency in:Identify quality objectives and standards with input from relevant stakeholders Develop quality metrics for the project and any product output in a quality management plan Select quality management methods and tools for resolving quality issues Consult with project team and stakeholders on quality requirements Your assessor will be looking for demonstrated evidence of your competency in the above. You are required to address the following: Task 2.1 Determine quality requirements Determine project quality requirements in consultation with stakeholders Develop a project quality plan Task 2.2 Case Study Determine project quality requirements in consultation with stakeholders Develop a project quality planAlthough the assessment requires group collaboration to simulate a work environment, the assessment submission is individual, and it will be marked as such.What do I need to do to complete this task satisfactorily?submit the completed assessment tasks, according to instructions, complete the tasks with sufficient detail and present them in a professional manner, use your own words and reference sources appropriately, meet the word count where required, use the scenario provided, use the templates provided where required, for your performance to be deemed satisfactory in this assessment task you must satisfactorily address all of the assessment criteria, if part of this task is not satisfactorily completed you will be asked to complete further assessment to demonstrate satisfactory performance.SpecificationsYou must deliver/participate in:Attend a project briefing session with the Project Sponsor in week 1 of class – Role Play in simulated work conditions Present and discuss the project quality plan with relevant stakeholders in week 3 – Role Play in simulated work conditions Discuss the requirements of the project quality plan (case study) in week 3 with relevant stakeholders – Role Play in simulated work conditionsYou must submit to GOALSNotes from the briefing session in week 1 Project quality management plan Summary of agreed on changes to the quality management plan Summary of feedback and inputs into the project quality plan (Case Study) Project quality management plan (Case Study)Resources and equipmentComputer with Internet access Access to Microsoft Office suites or similar software Learning material Scenario for assessment as provided Appendices as provided Relevant policies and procedures as provided Templates as providedRe-submission opportunitiesYou will be provided feedback on your performance by the Assessor. The feedback will indicate if you have satisfactorily addressed the requirements of each part of this task. If any parts of the task are not satisfactorily completed, the assessor will explain why, and provide you written feedback along with guidance on what you must undertake to demonstrate satisfactory performance. Re-assessment attempt(s) will be arranged at a later time and date. You have the right to appeal the outcome of assessment decisions if you feel that you have been dealt with unfairly or have other appropriate grounds for an appeal. You are encouraged to consult with the assessor prior to attempting this task if you do not understand any part of this task or if you have any learning issues or needs that may hinder you when attempting any part of the assessment. Complete the following activities: Task 2.1 Determine quality requirements This task requires you to: Determine quality requirements for the projectDevelop a quality management plan Distribute and discuss the project quality management plan with the project team and stakeholders Determine quality objectives Attend a briefing session with the trainer and assessor (who will play the role of Project Sponsor) in week 1 of class. During the briefing session, the Project Sponsor will illustrate the project, and you will have an opportunity to discuss the quality objectives and standards expected in the project. Take notes during the meeting to inform the project quality management plan (Task 2.1B). It is advisable to review the requirements of the project quality management plan to ask relevant questions. The trainer and assessor will validate your participation in the briefing session in the marking sheet. If you are absent from class, you are responsible for making alternative arrangements with the trainer and assessor to attend a briefing session. Duration: 45 minutes Summarise the notes taken during the briefing session in the space provided below. Project quality management plan Develop a project quality management plan (Template 1). Consult with the project sponsor (played by the trainer and assessor in the simulated work environment) as needed. Template 1 -Project Quality Management Plan Project overview Provide an overview of the project: name of the project, why it is undertaken, timelines and budget. (40-80 words) Project objectives and requirements List the project objectives (4-5) of the project and requirements (4-5) Project deliverables List the project deliverables (6-8) Project stakeholders Identify 8-10 project stakeholders (groups and/or individuals). Names and RolesResponsibilities, role or interest in the projectQuality requirements expected by the stakeholder group or individuals Project Quality Management Approach Quality Management ApproachObjectivesDetermine and list five quality objectives for the project.DevelopmentOutline all the following in a cohesive and comprehensive series of paragraphs: Mention what essential project requirements/objectives/needs are considered for quality planning Identify and list the significant inputs into the plan Mention any industry or organisational quality standards that are taken into consideration Describe the involvement of key stakeholders (specifically mention what stakeholders) in the development of the quality plan. Identify what specific policies and procedures are taken into consideration when developing the quality plan (100-150 words)Organisation, responsibilities and interfacesDetermine and record the primary roles and responsibilities of the project team and other critical stakeholders as related to project quality management. It could include coaching, mentoring, auditing processes, project reviews, provision of crucial knowledge and expertise. Add additional rows if needed.NameRoleQuality ResponsibilitiesQuality controlOutline all the following in a cohesive and comprehensive series of paragraphs: The plan for QC and QA: when they will be performed, tools and techniques that will be utilised, key personnel that will perform them. Any relevant information on how you will analyse the data. Process for recording the QC and QA data and how they will be communicated to relevant stakeholders. What process is in place if it is determined that quality standards do not comply with the standards defined in the plan at the end of the project? (100-150 words) Quality Planning Register Develop the register for each project deliverable. Project DeliverableQuality requirementsQA activitiesQC activitiesQuality standards/measurements and tools Communicate and discuss the project quality management plan Schedule a time with the trainer and assessor in week 3 of class to present the project quality management plan to the project sponsor (played by the trainer and assessor) and a group of relevant stakeholders (members of the project team and the project steering committee played by a group of classmates) in a simulated work environment. When presenting your work: Confirm quality objectives and standardsDiscuss and confirm quality metrics and requirements for each project deliverableNegotiate proposed roles and responsibilities for project quality managementConfirm quality assurance and control processes and practicesDemonstrate support for the quality management planUse active listening and questioning to elicit views and opinion of othersDocument feedback and inputs from the group of stakeholdersAdopt a collaborative approach Duration: 15 minutes. The trainer and assessor will evaluate your performance during the presentation and provide feedback on the marking sheet. If you are absent from class, you are responsible for making alternative arrangements with the trainer and assessor to present the project quality management plan. At the end of the meeting: Finalise the project quality management plan. Document the agreed changes in the table provided below: Agreed changesStakeholders’ expectationsQuality management approachQuality Planning Register Please note that the trainer and assessor will check that the agreed changes have been applied to the project quality management plan submitted with your assessment. Task 2.2 Case Study This task requires you to: Determine quality requirements for the projectDevelop a quality management plan Consider the following scenario. The Project Sponsor trusts your expertise in project management. The Project Sponsor asked you and your team to help with a project. The Marketing Team is organising an event to present the new campus to education agents. The Project Sponsor would like you to develop a quality management plan for this project. The plan will be used by the marketing team in charge of organising the event. Please note the event will be planned and delivered by existing staff only: the marketing team, and any other individual staff you believe should be included from the organisational chart. Please see details below: Event (Project)Presenting the new campus to education agentsType of eventVirtual event Zoom meetingStructurePowerPoint Presentation Q&ADuration1 hourBudget$1,500DateEvent Date: 20/6/20XX Note: event planning starts on 10/5/20XXPresenterMarketing ManagerOrganiserMarketing TeamAttendeesEducation Agents MMI -CEO MMI CFO Marketing Manager and Marketing team Academic ManagerRequirements for the human resource planSupport the marketing team with organising the event Ensure project roles are allocated according to planned work Schedule a time with the trainer and assessor in week 3 to discuss the requirements of the project quality management plan with the marketing team (played by a group of classmates) in a simulated work environment: Identify the quality objectives and standards in consultation with the marketing teamConsult with the marketing team on quality requirementsConsider inputs from the project sponsor, played by the trainer and assessor in simulated work conditionsDevelop a project quality plan The trainer and assessor will validate your active participation in the meeting with the marketing team and provide feedback on the marking sheet. If you are absent from class, you are responsible for making alternative arrangements with the trainer and assessor to present the project quality management plan. Summarise the feedback and inputs received from the marketing team and the project sponsor in the space provided below. (50-100 words) Develop a project quality management plan (Template 1) Template 1 -Project Quality Management Plan Project overview Provide an overview of the project: name of the project, why it is undertaken, timelines and budget. (40-80 words) Project objectives and requirements List the project objectives (2-3) of the project and requirements (2-3) Project deliverables List the project deliverables (4-6) Project stakeholders Identify 5-6 project stakeholders (groups and/or individuals). Names and RolesResponsibilities, role or interest in the projectQuality requirements expected by the stakeholder group or individuals Project Quality Management Approach Quality Management ApproachObjectivesDetermine and list three quality objectives for the project.DevelopmentOutline all the following in a cohesive and comprehensive series of paragraphs: Mention what essential project requirements/objectives/needs are considered for quality planning Identify and list the significant inputs into the plan Mention any industry or organisational quality standards that are taken into consideration Describe the involvement of key stakeholders (specifically mention what stakeholders) in the development of the quality plan. Identify what specific policies and procedures are taken into consideration when developing the quality plan (80-120 words)Organisation, responsibilities and interfacesDetermine and record the primary roles and responsibilities of the project team and other critical stakeholders as related to project quality management. It could include coaching, mentoring, auditing processes, project reviews, provision of crucial knowledge and expertise. Add additional rows if needed.NameRoleQuality ResponsibilitiesQuality controlOutline all the following in a cohesive and comprehensive series of paragraphs: The plan for QC and QA: when they will be performed, tools and techniques that will be utilised, key personnel that will perform them. Any relevant information on how you will analyse the data. Process for recording the QC and QA data and how they will be communicated to relevant stakeholders. What process is in place if it is determined that quality standards do not comply with the standards defined in the plan at the end of the project? (80-120 words) Quality Planning Register Develop the register for each project deliverable. Project DeliverableQuality requirementsQA activitiesQC activitiesQuality standards/measurements and tools

QUALITY: 100% ORIGINAL PAPER – NO PLAGIARISM – CUSTOM PAPER

Leave a Reply

Your email address will not be published. Required fields are marked *